Heritage Winnipeg

 

Eaton's Building
320 Portage Avenue

Update as of April 15th, 2002:

RE: True North proposal to demolish the Eaton's building and replace it with an arena

The following are matters that any party considering financing the proposed True North arena project should take into consideration:

Legal Challenges
The Save the Eaton's Building Coalition (SEBC) has two legal challenges to the project pending:
1. An application was filed in the Federal Court in December of 2001 regarding the process undertaken by Western Economic Diversification and the Treasury Board in approving the federal funds for the True North project. The coalition's contention is that the federal authority did not adequately conduct the requirements for the attribution of federal funds for the project in accordance with legislation.

2. An application was filed in the Court of Queen's Bench on March 14th regarding the process that was undertaken by the City of Winnipeg in approval of the Conditional Use Application and the Text Amendment to the Downtown Zoning By-Law. The Coalition has asked the Court to reject, on the basis and bad faith, the City of Winnipeg's decision on the text amendment.

Inadequacy of proposed facility
A group of Hockey fans calling themselves Winnipeg's Arena Quest have raised a number of concerns regarding the adequacy of the proposed Arena. Questions for this group may be directed to arenaquest@shaw.ca

Alternative Use for Eaton's Building
Architects and engineers have studied the building and agree that it is quite suitable for renovation for mixed commercial and residential use. A number of builders have expressed interest in such adaptation of the building. One builder with extensive experience has put forward a detailed plan. Such a development would be very beneficial to the downtown area.

Alternative Sites for Arena
We have encouraged True North to consider alternative sites for their arena. We believe that any alternative sites should go through the proper site selection process that considers facility access requirements, traffic, pedestrian safety and neighborhood impact.


Environmental Concerns
Socially conscious organizations should be concerned about the removal to landfills of the existing arena plus the Eaton's Building. Tons of debris will be needlessly removed.

Downtown Impact
Economic analyses on downtown arenas show that they have a negative impact on the immediate area. Downtown business and residents will be severely impacted. A majority of Winnipeggers agree that Portage Avenue is not the right place for an arena.

Public Safety
The Coalition's architect caucus has showed that the proposed arena facility, which will encroach onto Hargrave Street, will create serious safety concerns. A parking lot, laneway, bus stop, and tunnel (created by the building overhang) create "indefensible space" and threaten individual and neighborhood safety.

Financial Viability of the True North Project
Price comparisons with similar projects in Canada and the US suggest that the cost estimates of $125,000,000 may be low. The Mayor himself said in 1995 that an arena could not be built for less than $150 million dollars.

Public Subsidy
In order for the partners to make $3.7 million dollars a year in profit, the public sector contributes a minimum of $3.2 million dollars per year (VLT revenues and tax rebates).

Public Support
Despite the entrenched support of the Winnipeg Free Press and Winnipeg Sun for True North, the project does not have significant public support. The better people are informed, the less supportive they are. Our own professional poll results indicated by 2/3 of Winnipeggers prefer the retention and conversion of Eaton's into a mixed-use development that includes a housing component.

Provincial Implications
The present arrangement with True North prohibits the three level of government from funding a competing facility for 25 years. The exact clause in the May 14, 2001 termsheet reads:

Should some municipality outside Winnipeg, or Winnipeg itself wants to build a larger facility, it would be prevented from receiving public funds.

Information courtesy Save the Eaton's Building Coalition. For more information see the Save the Eaton's Building Coalition website: www.saveeatonsbuilding.ca
...........................................................
Eaton's Building- 320 Portage Avenue
UPDATE:
Please visit the Save The Eaton's Building Website under our Top Links for further information.
COURT INJUNCTION: Judge grants injunction to momentarily halt demolition
The Save the Eaton's Building Coalition is pleased to announce that it has received the judgment of Chief Justice Scott. The decision, which grants injunction on the demolition permit, disagrees with the contention of True North, the City of Winnipeg, and Court of Queen's Bench that the Save the Eaton's Building Coalition application "has no merit." The injunction will prevent the demolition permit from being issued by the City of Winnipeg until the Supreme Court of Canada decides whether or not to hear the Coalition's case.
Three key findings by the Judge:
1. Regarding the Coalition's application to the Supreme Court the judge stated, "Certainly, it cannot be said at this stage despite the fact that the applicant has been unsuccessful in all court proceedings to date, that its application is entirely without merit as submitted by the respondent."
2. On the issue of the lack of information the judge stated, "I am troubled by the lack of specificity in the information provided by the developer on behalf of the City …the fact remains that there still are, even after an 18 day adjournment, some important unanswered questions."
3. With respect to the delay the judge stated, "there is no evidence that withholding the demolition permit will cause significant delay to the developer or the City."
"In a precise 11-page decision, the learned judge has brought forward a decision of national importance, which advances the rights of citizens and democracy," concludes Christine Common-Singh.
.....................................................................
Zoning: Text Amendment Decision
Many of you have been following the drama around the issue of zoning for the proposed arena. The appeal for the conditional use was laid over due to unconventional actions undertaken by True North's lawyer. In the end, the text amendment was approved by City Hall in spite of hearing a day's worth of delegations from those deeply troubled by the possibility of allowing an arena to be a permitted use throughout more of our downtown. The test amendment was ratified by City Council on February 27, 2002.
.....................................................................
Survey Says Keep Eaton's Building
Public Prefers Converting the Eaton's Building and Constructing Arena on an Alternative Site
The Save the Eaton's Building Coalition released results of a public opinion survey conducted by Prairie Research Associates during October 17 to 24, 2001. The results demonstrate very strong support for building Eaton Square.
.....................................................................
Save The Eaton Building Coalition

The save the Eatons Building Coalition is an ad-hoc group of architects, historians, planners, artists, activists and downtown residents who have joined forces to plan for the ongoing use of the former Eaton's Building at 320 Portage Avenue. The group opposes the demolition and dereliction of the Eaton's Building. The coalition believes that the building should be protected because of its historical, architectural and social significance. They believe that the adaptive re-use of the Eaton's Building can play a role in promoting the health of downtown Winnipeg.

For further information about the Save the Eatons Building Coalition, visit www.saveeatonsbuilding.ca

History of The T. Eaton Company Store- In the spring of 1904, John Craig Eaton (1876-1922), son of Timothy Eaton (1834-1907), took a scouting trip to Winnipeg to spy out a potential location for the Eaton’s store. Eaton’s saw that Portage Avenue was at the beginning of its rise, at a time when Winnipeg had boundless horizons in terms of prosperity. By summer of 1904, construction had started. The building was to be five-storeys with a wooden, partial sixth floor, of steel frame construction atop a pyramidal stone foundation. The total cost of the building was $350,000.

Everything about the new store was large– the largest building in the city, the most floor space and the most merchandise. Even before the store opening, local commentators were stating that Eaton’s had made a strong difference to Portage Avenue, proclaiming that the area around Eaton’s was now a strong rival to Main Street.

By November 1906, plans were already made to extend the store along Donald Street. The new addition was to have another entrance near the south end, as well as an interior broad staircase, two new passenger elevators, two new freight elevators, and a “magnificent” marble soda fountain opposite the existing Donald Street elevators. Among the new features of the addition was a churning department, where one could get free samples of butter.

Late in 1908, it was once more announced that Eaton’s was expanding. This entailed an additional floor on the existing store, as well as a “brick and steel” warehouse on Graham Avenue.

The death of Sir John Craig Eaton in 1922 has been described as a “seismic event for Eaton’s”. The operation was given to a cousin, Robert Young Eaton, and the proposed expansion of a 12-storey Mail Order Building on the corner of Graham Avenue and Hargrave Street was considered unnecessary by him. This was in direct opposition to the late J. C. Eaton.

Eaton place was opened by Mrs. John David Eaton in 1979, but financial problems and economic downturn in the 1980’s brought the loss of Eaton Place in the 1980’s. Once a flagship store, the Portage Avenue landmark survived cost-cutting operations in 1997 which saw the closure of other Eaton’s outlets. The final act came the summer of 1999 when Eaton’s declared bankruptcy and a two-month sale of its assets ensued. The once great retailing/mail order empire closed its doors on 19 October 1999.

The Heated Eaton's Debate

A $125-million, 15,000 seat arena and entertainment complex is scheduled to replace the existing Eaton’s building on Portage Avenue. Here are some of the facts:

- The three levels of government will contribute a total of $38-million of the $125-million (approx. $10-million per level).
- The City of Winnipeg is also contributing $3.5-million from its capital budget on road and sewer work, plus rebating the amusement tax and exempting the new arena from business tax.
- Eaton’s closed its door in 1999, but City Council would not give it historical status (only building owners can apply for historic designation).
- The current owner of the Eaton’s building is Osmington Inc.
- Investors of the True North project include the Chipman family, Crocus Investment Fund, Osmington Inc., and David Graves.
- Architects working on the project are Sinks Combs Dethlefs of Denver.
Update on Important Issues from the Save the Eaton's Building Coalition from January 2002:

The Battle Continues Into 2002
1. Important Public Hearing
Date: Tuesday, January 8, 2002, 1:30 p.m.
Place: Council Chamber, Council Building, City Hall, 510 Main St.
The City of Winnipeg is proposing to amend the text of the Downtown Winnipeg Zoning By-law to allow the construction of the True North Arena project. A Public Hearing is a requirement for an amendment to the text of the By-law and anyone who attends has the right to speak. This will be the last chance to express to City Councillors your views on the demolition of the Eaton's Building and the building of the True North Arena on its "too-small site".

Details of the application follow:
Committee: Standing Policy Committee on Property and Development (Councillors Vandal (Chair), De Smedt, O'Shaunessy, Prystanski and Mayor Murray)
Applicant: Director of Planning, Property and Development, City of Winnipeg
File: DAZ 225/01

Proposal: The Director of Planning, Property and Development proposes to amend the text of By-law No. 4800/88 to add the use "Sports, Entertainment, Cultural Facility" as a permitted principal use to the Non-residential Use Groups designated as "NRc" and "NRd".
Information: Phone Mr. M. Sandhurst, Senior Planner at 986-5066. He will fax the Planning Report to you.

Representations: Anyone who attends the hearing may request to speak. However the Clerk of the Committee would prefer that you notify her in advance: Ms. J. Park, Clerk of the Committee on Property and Development - PH 204.986.3732; FX 204.947.3452; jpark@city.winnipeg.mb.ca

2. Legal Matters
a. Application to the Supreme Court of Canada
The Supreme Court is considering the Coalition's application to hear its case against the City of Winnipeg. We contend that there is evidence of bias and bad faith in the City's manipulation of process to prevent the designation of the Eaton's Building as a heritage structure. Our motion for an injunction to prevent the demolition of the building until the case has been decided has been sent back to Manitoba's Court of Appeal. Chief Justice Scott will consider this motion on Thursday, January 10, 2002 at the Law Courts Building at Kennedy and York. (Time to follow)

b. Application to the Federal Court
The Coalition has also made application to the Federal Court of Canada requesting a judicial review of the Environmental Assessment process. Environmental Screening of the True North Arena project was a requirement before the federal $millions could be handed over to the private owners of the arena. The Coalition contends that there were important errors and omissions in the carrying out of the environmental process. It may be six months before this case is heard.

c. Application to Manitoba's Court of Queen's Bench
When the City of Winnipeg was trying to push through approval of the True North Arena by labelling it a permitted "retail business", the Coalition made application to the Court of Queen's Bench for a judicial interpretation of the Downtown Winnipeg Zoning By-law. This case is scheduled to be heard on Thursday, January 17, 2002. However, the City is now proposing to amend the text of the By-law (see above) and the case may not proceed.

3. Chronology of Coalition Initiatives
Although you have not heard from us for a while, members of the Coalition have continued to meet with officials and carry out other initiatives. David Lettner has prepared the following chronology for your interest:

CHRONOLOGY OF KEY PLANNING MILESTONES AND MEETINGS

JUNE 2001
05.06.01: First organizing meeting of citizens at River Heights C.C.
10.06.01: First organizing meeting of the SEBC
12.06.01: P&D Committee hearing on heritage designation for T. Eaton Co. building
13.06.01: EPC meeting on heritage designation for T. Eaton Co. building
20.06.01: Council decision to not designate T. Eaton Co. building as Grade II structure
25.06.01: First meeting of Eaton Square (ESQ) concept development team

JULY 2001
03.07.01: Meeting with NDP Caucus
04.07.01: Meeting with LIB and PC Caucus
17.07.01: Meeting with Mr. Duhamel’s MRO staff
17.07.01: Meeting with provincial staff of the CEDC of Cabinet
21.07.01: Meeting with Senator Carstair’s MRO staff
26.07.01: Media Conference No.1: ESQ Concept Launch

AUGUST 2001
08.08.01: Meeting with Ministers Friesen and Lemieux
10.08.01: SEBC release of 1997 LM reports supporting adaptive reuse of the Eaton bldg
16.08.01: Media Conference No.2: SEBC release of True North Biz Plan dated July/00
30.08.01: Media Conference No.3: SEBC announces legal challenge to Appeal Court

SEPTEMBER 2001
05.09.01: SEBC delegations meet with MP Anita Neville and WFP Editor Nick Hirst

OCTOBER 2001
03.10.01: Media Conference No.4: SEBC announces developer interest in ESQ
10.10.01: Presentation to Downtown Rotary Club
30.10.01: Fundraising Event No.1: Luncheon with Allan Gotlieb

NOVEMBER 2001
01.11.01: Media Conference No. 5: SEBC announces results of public opinion survey
13.11.01: SEBC application to Court of Queen’s Bench on zoning matter
15.11.01: ZBL matters: Board of Adjustment Hearing
22.11.01: ZBL matters: P&D considers True North request for text amendment

DECEMBER 2001
05.12.01: Fundraising Event No.2: SOS Art Sale
06.12.01: ZBL matters: P&D adjourns appeal hearing based on TN manipulation
11.12.01: ZBL matters: P&D sets public hearing date for TN text amendment

JANUARY 2002
08.01.02: ZBL matters: P&D public hearing on text amendment
09.01.02: ZBL matters: EPC to consider recommendations of P&D on text amendment
17.01.02: ZBL matters: SEBC Court of Queen’s Bench date on zoning matter
30.01.02: ZBL matters: Council decision on EPC recommendation for text amendment


Prepared and compiled by David E. Lettner.
After hearing superb presentations from many of the Save the Eaton's Building Coalition supporters today, the Standing Committee on Property and Development voted to postpone its decision on a text amendment to Downtown Winnipeg Zoning By-law 4800/88 until a meeting in three weeks time. The delay will allow time for Planning Officials:

to develop a definition for the term "Sports, Entertainment, Cultural Facility"

to clarify the intent of the addition to the By-law

to study possible detrimental effects of the text amendment

to establish a means of "checks and balances" (Councillor Peter De Smedt's term) if the text amendment does go ahead

We do not think the City will issue the Demolition Permit to True North until the zoning issues have been resolved.

It appears that our lobbying is finally starting to have an effect. Councillors today appeared much less firm in their resolve to push the arena through at all costs. Thanks for all of the work that everyone continues to put into this effort.

Heritage Winnipeg would like to acknowledge this information from members of the Save The Eaton's Coalition; taken from their website at www.saveeatonsbuilding.ca. Thank you for their ongoing efforts.